Zambia Gold Concession :

  • Split the Alluvial Gold target areas in 18621 HQ LPL into ten (10 ) segments
  • At Phse1: Five (5) segments to be converted in to  Five (5) SPP (Small scale prospective permits)  by 30th November 2014 for Five years life span
  • Phase 2: Five (5) segments to be converted in to  Five (5) SPP (Small scale prospective permits) 31st January 2015 for Five years life span
  • Phase 3: Converting Two (2) SPP into two(2)SML (Small Scale Mining License) by 15th May 2015 for Ten (10 )years life span
  • Phase 4: Starting of commercial Alluvial Gold Mining
  • Phase 5: Converting additional three (3) SPP into three (3) SMLs by August 2015
  • Phase 6: Converting additional Five (5) SPP into Five (5) SMLs by December 2015
  • Phase 7: Exploration on Hard rock for residual gold
  • Phase 8: Colluviums and  Residual Gold mining by 15th April 2017